ICC |
Insurance Claims
Consultants |
|
|
|
|
| |
 |
Bakun Hydro Project,
Philippines |
|
|
 |
The 70MW Bakun
Hydroelectric Project, a traditional run of the river scheme
in northern Luzon, comprises a 9.6km long “horse-shoe” shaped
tunnel, constructed by Drill+Blast, which transfers water from the
weir/intake structures to the two 35MW turbines located in a surface
powerhouse some 579m below.
ICC were retained to
advise and assist in determining whether any damage had occurred to
the nominally unlined tunnel and to the confined steel pipeline
during the commissioning of the facility and thus establish whether
there was a valid claim.
|
|
|
 |
|
|
Bakun Hydro Project, Philippines |
|
|
 |
|
Tunnel Excavation

| |
|